What is Fence Planning: Posts, Pickets, Rails — The Exact Quantities Formula?
Mathematical Foundation
Laws & Principles
- Nominal vs Actual Lumber: A '6-inch' picket is actually 5.5". A '4-inch' picket is 3.5". Always use actual dimensions — nominal sizing will cause your pickets to not reach the end of the fence.
- 1/3 Post Burial Rule: Bury 1/3 of total post length, minimum 24 inches. For a 6-foot fence, use 9-foot posts with 3 feet buried. Frost line depth varies by region — check your local codes.
- Concrete per Post: One 50-lb bag of fast-setting concrete per 4×4 post at 8-ft spacing. Use two bags for 6×6 posts or gate posts. Do NOT skip concrete — a post without concrete shifts within 2 years.
- Gate Post Doubling: Gate posts carry a cantilevered load. Use doubled 4×4 posts or a single 6×6. These do not count in the standard post spacing formula — they are additional structural members.
- Ground Contact Rating: Posts MUST be ground-contact-rated pressure-treated lumber (UC4A or UC4B). Above-ground-rated PT lumber (UC3B) will rot below grade within 3-5 years.
Step-by-Step Example Walkthrough
" Building a 120-foot privacy fence with 5.5-inch cedar pickets (0 gap), posts every 8 feet. "
- 1. Posts: ⌈120 ÷ 8⌉ + 1 = 15 + 1 = 16 posts.
- 2. Pickets: ⌈120 × 12 ÷ 5.5⌉ = ⌈261.8⌉ = 262 pickets.
- 3. Rails: 15 spans × 2 rails/span = 30 rails (8 ft 2×4s).
- 4. Concrete: 16 posts × 1 bag = 16 bags of 50-lb fast-set.